By Nick Pedley
News Editor 

Hartley council receives CIIP update

Pipe-lining project to take place in winter months

 

August 11, 2022

The Hartley City Council on Monday heard an update on a project that will improve existing infrastructure on the east side of town.

Engineer Wes Boyer, of Bolton & Menk, said work on the cure-in-place-pipe (CIPP) lining project is slated to start in December. The scope of the project will affect 11,000 feet of pipe and 46 manholes.

"It's really not a problem to be doing it in the winter. They do it regularly because the pipes are underground and fairly protected from temperatures," Boyer said. "The manholes will be handled more towards spring because they are more open to the air."

CIPP lining...