Work to slow at Everly sewage lagoons
Construction company moving on to new job
June 18, 2020
BY NICK PEDLEY
Despite noticeable progress this spring, it's unlikely improvements at Everly's sewage treatment lagoons will be completed this year.
Engineer Brian Schmidt said Monday during an update to the city council that most dirt work for Phase 1 of the project has been completed. However, crews from King Construction will be moving to a new job soon, making it unlikely all of the upgrades are finished before snow flies.
"I'm not as optimistic as I was a couple weeks ago after talking with them," Schmidt said. "I'm trying to work more with the DNR to put a little more pressure on them...